Rapid data center growth is testing electricity planning, generation and transmission. The size of the challenge — and who should pay for it — remains under debate.
The data center boom is becoming an electricity story.
As artificial intelligence, cloud computing and other digital services expand, developers are proposing increasingly large facilities that can require hundreds of megawatts of continuous power. That has pushed questions about generation, transmission, grid reliability and electricity costs into the center of the data center debate.
The scale is significant, although forecasts vary.
Lawrence Berkeley National Laboratory estimated that U.S. data centers consumed about 176 terawatt-hours of electricity in 2023, or approximately 4.4% of total U.S. electricity use. Its 2024 report projected that data centers could account for 6.7% to 12% of U.S. electricity consumption by 2028, depending on how quickly facilities are built and how overall electricity demand changes.
More recent modeling from the Electric Power Research Institute, or EPRI, puts the potential share even higher later in the decade. Its 2026 scenarios estimate that data centers could consume 9% to 17% of U.S. electricity by 2030, compared with roughly 4% to 5% today. The wide range reflects uncertainty about how many announced projects will actually be constructed and how quickly they will begin operating.
Globally, the International Energy Agency expects data center electricity consumption to more than double by 2030, with the United States accounting for the largest share of projected growth. The IEA says renewables, natural gas, nuclear generation, storage and other resources are all likely to play roles in meeting that demand.
The Issue Is Not Only How Much Power — But Where and When
National electricity totals can obscure the more immediate challenge: data centers tend to cluster.
EPRI estimates that Virginia already has the highest concentration of data center electricity consumption in the country. Under its 2030 scenarios, several additional states could see data centers account for more than 20% of statewide electricity demand.
That concentration matters because generation and transmission infrastructure cannot always be expanded as quickly as a large data center can be planned.
PJM Interconnection, which coordinates the electric grid across 13 states and the District of Columbia, is among the regions confronting rapid large-load growth. The Federal Energy Regulatory Commission has directed PJM to develop clearer rules for serving large loads, including data centers that locate alongside generating plants. FERC said the rules must address reliability while also protecting consumers from inappropriate cost shifting.
Another complication is determining how much proposed demand is real.
Reuters reported this month that data center grid requests nationally have become much larger than the electricity currently consumed by operating facilities. Some projects may be submitted to multiple utilities or may never reach construction, creating what planners have described as speculative or “ghost” demand. Utilities and regulators are responding with deposits, financial requirements and additional project verification intended to improve forecasting.
Who Pays for Grid Expansion?
This is one of the most contested questions.
Large new customers can require new substations, transmission lines, generation and other infrastructure. Regulators must determine how those costs are divided among data center operators, utilities and other electricity customers.
There is evidence supporting different concerns.
The Data Center Coalition released an analysis by consulting firm Energy + Environmental Economics in May that reviewed more than 10 studies and reported no historical evidence that data centers, under existing rate structures, have been responsible for increases in residential electricity costs. The analysis argued that fuel costs, infrastructure replacement, extreme weather and other factors also affect rates.
At the same time, FERC and state regulators are actively examining future cost allocation precisely because very large new loads may require substantial new infrastructure. That means past rate effects do not necessarily answer how costs should be allocated as data center demand grows.
Texas has become one of the clearest examples of the tension. State officials recently moved to require stronger verification of large-load projects and are examining their impact on grid infrastructure, costs and water use.
Can New Generation Solve the Problem?
Generation is part of the solution, but not the entire answer.
EPRI projects that natural gas could provide a substantial portion of incremental U.S. electricity supply under current-policy scenarios, while renewable generation, storage, nuclear power and emerging technologies may also contribute depending on corporate commitments, economics and project timelines.
Some data center developers are also pursuing onsite generation, colocating near existing power plants, contracting directly for new generation or exploring advanced nuclear and geothermal technologies.
But building generation does not eliminate transmission constraints. Electricity must still move through a grid designed around specific locations, load patterns and reliability requirements.
What This Means for Labor
For the building trades, the power challenge expands the data center story well beyond the facility itself.
Meeting new electricity demand can require transmission lines, substations, generation facilities, battery storage, electrical equipment, pipelines, cooling systems and other infrastructure. That can translate into work for electricians, lineworkers, operating engineers, laborers, pipefitters, ironworkers and other skilled trades.
It also raises a workforce planning question. If electricity infrastructure must expand at the same time as data center construction, both sectors will compete for many of the same skilled workers.
That makes apprenticeship capacity and workforce development part of the grid conversation.
Key Takeaways
- U.S. data center electricity demand is growing rapidly, but forecasts vary substantially because many proposed facilities may not ultimately be built.
- Berkeley Lab estimated data centers used about 4.4% of U.S. electricity in 2023; EPRI projects a possible 9% to 17% share by 2030.
- The challenge is regional as much as national because data centers tend to cluster in markets with available land, fiber and power.
- Regulators are developing new rules around interconnection, reliability and who pays for infrastructure upgrades.
- Evidence about current residential rate impacts is mixed with concerns about future costs; rate design and cost allocation matter.
- New generation will be necessary, but transmission, substations and other grid infrastructure must also expand.
- For labor, data center growth may create work not only inside data center construction but across the wider power and transmission system.
LaborForce Media Takeaway
The question is not simply whether the grid can support more data centers. It is whether generation, transmission, workforce capacity and regulatory planning can expand at roughly the same pace as the projects seeking electricity.
There is no single national answer. Conditions vary considerably by region.
What is clear is that the infrastructure behind the data center boom now extends far beyond server buildings themselves. Power has become one of the defining constraints — and one of the largest infrastructure challenges — of the AI era.
References and Links
Lawrence Berkeley National Laboratory — 2024 United States Data Center Energy Usage Report
Foundational U.S. report estimating historical electricity consumption and future demand scenarios through 2028.
2024 U.S. Data Center Energy Usage Report
EPRI — Powering Intelligence 2026
Projects data centers could account for 9% to 17% of U.S. electricity consumption by 2030 and examines regional differences and supply options. EPRI Powering Intelligence 2026
International Energy Agency — Energy and AI
Projects global data center electricity consumption will more than double by 2030 and examines the generation sources likely to serve new demand. IEA Energy and AI Executive Summary
International Energy Agency — Electricity 2026
Examines broader global electricity demand growth through 2030, including data centers, industry, transportation and cooling. IEA IEA Electricity 2026
Federal Energy Regulatory Commission — PJM Large-Load Rules
Describes FERC’s direction to PJM to establish clearer rules for data centers and other large loads while addressing reliability and consumer protection. FERC Data Center and Large Load Order
PJM Interconnection — Load Forecasting
Provides PJM’s current long-term load forecast materials and data center forecasting resources. PJM Load Forecast Development
Data Center Coalition / E3 — Understanding the Drivers of Rising Electricity Rates
Industry-commissioned study concluding that historical evidence does not show data centers driving higher residential electricity costs under existing rate structures. DCC/E3 Electricity Rate Study
Reuters — Data Center “Ghost Demand” and Grid Planning
Reports on regulators’ concerns that speculative or duplicate grid requests may exaggerate future electricity demand and complicate infrastructure planning. Reuters: Data Center Grid Demand and Planning